Crews are approaching completion of the new inside lane on the westbound Interstate 4 (I-4) exit ramp to eastbound State Road (S.R.) 528 (Beachline Expressway) at Exit 72. Upon completion, this widening project will double the capacity of the ramp linking these two major roadways in Orange County.
In December, crews conducted two traffic shifts and finished striping on the right lane of westbound I-4 approaching Exit 72. Paving operations on the ramp also progressed and new guardrail was installed.
Final ramp paving is expected to be completed in January. Crews will also install posts for new overhead signs and permanent lighting fixtures along westbound I-4. Once these operations are completed, crews will complete final work and clear the construction zone of equipment and debris to prepare the project for final inspection.
The project began in January 2024 and is anticipated to reach completion April 2026.
For more information, visit the project website at I4Beyond.com/SR528.

I-4 Beyond the Ultimate: 2025 Wrapped
60 Never Looked so Good: Happy Birthday, I-4!
Cold Weather Brings Unique Construction Challenges
What’s Next for the New Loop Ramp on Apopka-Vineland Road