Segment 2 (242484-7)

Segment 2 of the I-4 Beyond the Ultimate project picks up right where the I-4 Ultimate project leaves off. Motorists will have seamless travel while driving on I-4 through the three interchanges within Segment 2.

Segment 2 features the construction, widening and/or replacement of 23 bridges. In addition to 13 existing stormwater ponds, the crews will build an additional nine new ponds.

Length 4.6 miles

Boundaries From west of Kirkman Road (S.R. 435) to just east of Central Florida Parkway

Cost Construction (w/Design): $760M

Funding Currently funded construction in 2020

Special features Modified Diverging Diamond Interchange at Sand Lake Road with new access to Turkey Lake Road Direct connect ramps between I-4 and S.R. 528 Express Lanes Adding ramps at Central Florida Parkway from westbound I-4 and to eastbound I-4

FDOT Project Manager


Todd Helton, P.E.
386-943-5207
todd.helton@dot.state.fl.us

Design Engineer

Jacobs
Scott Bear, P.E.
Scott.Bear@jacobs.com